Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1638730.015
Citation: 01004B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/20/2023
Nr Instances: 2
Nr Exposed: 20
Abatement Date: 04/03/2023
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order: 04/12/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/12/2023 | $0.00 | 04/03/2023 | Serious | |
Penalty | Z: Issued | 03/20/2023 | $0.00 | 04/03/2023 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed including, but not limited to, 29 CFR 1910.147(c)(6)(i)(A), (c)(6)(i)(B), (c)(6)(i)(C) and (c)(6)(i)(D): a) On or about December 13, 2022, the employer failed to conduct a periodic inspection to correct deviations or inadequacies with the Drain Belt's energy control procedure pursuant to 29 CFR 1910.147(c)(6)(i)(B). b) On or about December 13, 2022, the employer failed to conduct a periodic inspection to correct deviations or inadequacies with the Shrink Tunnel's energy control procedure pursuant to 29 CFR 1910.147(c)(6)(i)(B).