Violation Detail
Standard Cited: 19260651 H03 Specific Excavation Requirements.
Inspection Nr: 1426821.015
Citation: 01004B
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/13/2019
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 10
Report ID: 0419400
Contest Date: 01/30/2020
Final Order: 08/20/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 08/20/2020 | $0.00 | Serious | ||
| Penalty | C: Contested | 05/11/2020 | $0.00 | Serious | ||
| Penalty | Z: Issued | 12/13/2019 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1926.651(h)(3): Where excavation work interrupted the natural drainage of surface water (such as streams), diversion ditches, dikes, or other suitable means were not used to prevent surface water from entering the excavation and to provide adequate drainage of the area adjacent to the excavation. (a) Lamey Bridge Rd. - On or about August 27, 2019 the employer did not provide a suitable diversion for water flowing into the excavation, exposing employees to caught in hazards.
Translate