Violation Detail
Standard Cited: 19100036 H03 Design and construction requirements for exit routes.
Inspection Nr: 1021840.015
Citation: 01004B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/24/2015
Nr Instances: 1
Nr Exposed: 10
Abatement Date: 07/21/2015
Gravity: 5
Report ID: 0418100
Contest Date:
Final Order: 07/16/2015
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/16/2015 | $0.00 | 07/21/2015 | Serious | |
Penalty | Z: Issued | 06/24/2015 | $0.00 | 07/21/2015 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1910.36(h)(3): Outdoor exit route(s) were not reasonably straight and did not have smooth, solid, substantially level walkways. On 1/28/15, at Plant 4, the employer did not ensure the emergency egress discharge leading outdoors from the paint area had solid and level walkways. Discharge from the area was concrete and dirt path that was broken creating an uneven surface. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).