Violation Detail
Standard Cited: 19100219 C03 Mechanical power-transmission apparatus.
Inspection Nr: 1649574.015
Citation: 01004A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,349.00
Current Penalty: $0.00
Issuance Date: 07/17/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 01/05/2024
Gravity: 5
Report ID: 0112300
Contest Date: 08/10/2023
Final Order: 01/05/2024
Related Event Code (REC): C;I
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 01/05/2024 | $0.00 | 01/05/2024 | Serious | |
| Penalty | C: Contested | 08/10/2023 | $3,349.00 | 08/03/2023 | Serious | |
| Penalty | Z: Issued | 07/17/2023 | $3,349.00 | 08/03/2023 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.219(c)(3): Vertical or inclined shafting seven feet or less from floor or working platform was not enclosed with stationary casing(s): (a) Wastewater Pretreatment Slurry Tank adjacent to Tumbling Area: On or about February 9, 2023, the inclined shafting on the spindle mixer used in the batching tank was not protected by stationary casing(s) enclosing shafting completely or by trough(s) enclosing sides and top or sides and bottom of shafting, exposing employees to the spinning shaft when adding materials to the tank.
Translate