Violation Detail
Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
Inspection Nr: 1461749.015
Citation: 01004A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $13,494.00
Current Penalty: $11,469.90
Issuance Date: 07/06/2020
Nr Instances: 1
Nr Exposed: 500
Abatement Date: 07/30/2020
Gravity: 10
Report ID: 1032500
Contest Date: 07/29/2020
Final Order: 04/07/2021
Related Event Code (REC): C
Emphasis:
Substance: 0640
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/07/2021 | $11,469.90 | 07/30/2020 | Serious | |
Penalty | C: Contested | 08/05/2020 | $13,494.00 | 07/30/2020 | Serious | |
Penalty | Z: Issued | 07/06/2020 | $13,494.00 | 07/30/2020 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.119(j)(2): The employer did not establish or implement written procedures to maintain the on-going integrity of process equipment: a) Lurgi Plant: The employer has not developed procedures for preventative maintenance and inspections performed on valve HCV 5145 and the valve position controller. Note: Abatement documentation and certification are required for this item.