Violation Detail
Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1298176.015
Citation: 01004A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,315.00
Current Penalty: $5,500.00
Issuance Date: 04/11/2018
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 05/29/2018
Gravity: 5
Report ID: 0729300
Contest Date:
Final Order: 05/09/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/09/2018 | $5,500.00 | 05/29/2018 | Serious | |
Penalty | Z: Issued | 04/11/2018 | $8,315.00 | 05/29/2018 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s): a. In the zinc building, lockout had not been performed on machine number 7-021, for approximately three months because the lockout disconnect was in disrepair. b. In the aluminum building, an interlock gate was used for energy isolation, on machine number 7-002, on 2-26-18. Abatement documentation is required for this violation.