Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 1297656.015
Citation: 01004A
Citation Type: Serious
Abatement Status:
Initial Penalty: $12,934.00
Current Penalty: $0.00
Issuance Date: 08/24/2018
Nr Instances: 3
Nr Exposed: 4
Abatement Date: 09/13/2018
Gravity: 10
Report ID: 0625500
Contest Date:
Final Order: 09/18/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/18/2018 | $0.00 | 09/13/2018 | Serious | |
Penalty | Z: Issued | 08/24/2018 | $12,934.00 | 09/13/2018 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.119(j)(2): The employer did not implement written procedures to maintain the on-going integrity of process equipment: On or about February 27, 2018, where the employer's did not implement written procedures to maintain the on-going mechanical integrity of process equipment at the DCP Midstream Sonora Gas Plant for process equipment including, but not limited to the following: a) Level switch high shutdown 151 (P&ID FS-010 Rev.23) b) Level switch high shutdown 153 (P&ID FS-010 Rev.23 c) LSLL 140 Level Switch Low Shutdown