Standard Cited: 19100303 B07 General.
Inspection Nr: 1213053.015
Citation: 01004A
Citation Type: Serious
Abatement Date: 06/22/2017 2
Initial Penalty: $6,519.00
Current Penalty: $4,502.00
Issuance Date: 06/12/2017
Nr Instances: 3
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0317500
Contest Date:
Final Order: 06/23/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/23/2017 | $4,502.00 | 06/22/2017 | Serious | |
Penalty | Z: Issued | 06/12/2017 | $6,519.00 | 06/22/2017 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.303(b)(7): Electric equipment was not installed in a neat and workmanlike manner: Instances including, but not limited to, the following: a) Job site, 5125 Baum Boulevard, Pittsburgh, PA: On or about February 23, 2017, at bay 2 in the lower bay, the employer did not ensure that electrical equipment was properly installed in that electrical wiring was joined with a wire nut and left open and exposed to contact. b) Job site, 5125 Baum Boulevard, Pittsburgh, PA: On or about February 23, 2017, at bays 3 & 4 in the lower bay, the employer did not ensure that electrical equipment was properly installed in that broken/damaged conduit existed. c) Job site, 5125 Baum Boulevard, Pittsburgh, PA: On or about February 23, 2017, at bay 2 in the lower bay, the employer did not ensure that electrical equipment was properly installed in that an outlet box was not secured to a structure, but rather was allowed to freely hang on flexible type conduit.