Powered by GoogleTranslate

Violation Detail

Standard Cited: 19100305 B01 II Wiring methods, components, and equipment for general use.

Inspection Nr: 943256.015

Citation: 01004

Citation Type: Serious

Abatement Status: Corrected During Inspection

Initial Penalty: $2,550.00

Current Penalty: $2,550.00

Issuance Date: 04/10/2014

Nr Instances: 2

Nr Exposed: 6

Abatement Date:

Gravity: 1

Report ID: 0418400

Contest Date:

Final Order: 05/23/2014

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 05/23/2014 $2,550.00   Serious  
Penalty Z: Issued 04/10/2014 $2,550.00   Serious  

Text For Citation: 01 Item/Group: 004 Hazard:

29 CFR 1910.305(b)(1)(ii): Unused openings in boxes, cabinets, or fittings were not effectively closed: a) Paper machine #1, west side wall in the basement  on or about February 5, 2014, the 480-volts electrical disconnect panel box had an unused opening on the right side from a missing knockout, exposing employees to electrical shock hazards. b) Paper Machine #1, inside the MCC Room - on or about February 05, 2014, a breaker panel had unused openings in the face plate, exposing employees to an electrical shock hazard. ABATEMENT CERTIFICATION IS NOT REQUIRED

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.