Violation Detail
Standard Cited: 19260405 B02 Wiring methods, components, and equipment for general use.
Inspection Nr: 935687.015
Citation: 01004
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $1,080.00
Current Penalty: $540.00
Issuance Date: 11/29/2013
Nr Instances: 3
Nr Exposed: 3
Abatement Date: 12/18/2013
Gravity: 1
Report ID: 0316100
Contest Date:
Final Order: 12/12/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/12/2013 | $540.00 | 12/18/2013 | Serious | |
| Penalty | Z: Issued | 11/29/2013 | $1,080.00 | 12/18/2013 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1926.405(b)(2): All pull boxes, junction boxes, and fittings were not provided with covers: a) On August 20, 2013 and at times prior thereto; first floor; employees were using unguarded energized outlets either plugged in directly or by portable extension cords to power electrical equipment, such as but not limited to saws and other tools used in the process. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Translate