Violation Detail
Standard Cited: 19100304 G05 Wiring design and protection.
Inspection Nr: 925114.015
Citation: 01004
Citation Type: Serious
Abatement Date: 01/02/2014 2
Initial Penalty: $2,800.00
Current Penalty: $2,800.00
Issuance Date: 11/27/2013
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0728500
Contest Date:
Final Order: 12/23/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 11/27/2013 | $2,800.00 | 01/02/2014 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.304(g)(5): The path to ground from circuits, equipment, and enclosures was not permanent, continuous, and effective: (a) North Bay, or Drive Through Bay: Mechanics were exposed to electrical hazards as the EcoXtreme Snapon AC Recovery Machine was not grounded as the grounding pin was absent. Abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records. NOTE: IN ADDITION TO ABATEMENT CERTIFICATION, THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT DOCUMENTATION FOR THIS ITEM. FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19