Violation Detail
Standard Cited: 19100219 F03 Mechanical power-transmission apparatus.
Inspection Nr: 1666532.015
Citation: 01004
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,831.00
Current Penalty: $4,000.00
Issuance Date: 09/28/2023
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 10/25/2023
Gravity: 5
Report ID: 0336000
Contest Date:
Final Order: 10/17/2023
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/17/2023 | $4,000.00 | 10/25/2023 | Serious | |
| Penalty | Z: Issued | 09/28/2023 | $6,831.00 | 10/25/2023 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.219(f)(3):Sprocket wheels and chains which were seven (7) feet or less above floors or platforms were not enclosed: A.) International Timber & Veneer, LLC, Boiler Room, on or about 4/28/23 and times prior thereto: Employees were working and walking around exposed rotating parts located approximately 3 feet above the floor. The rotating parts include but are not limited to. chain and sprocket system used to power an auger under the feed line conveyor B.)International Timber & Veneer, LLC, Boiler Room, on or about 6/28/23 and times prior thereto: the guard for chain and sprocket drive was inadequate as there was a hole in the guard. Chain and Sprocket located approximately 3 feet above the ground. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Translate