Standard Cited: 19100305 J02 V Wiring methods, components, and equipment for general use.
Inspection Nr: 1665818.015
Citation: 01004
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $10,938.00
Current Penalty: $6,562.80
Issuance Date: 10/20/2023
Nr Instances: 3
Nr Exposed: 7
Abatement Date:
Gravity: 10
Report ID: 0626000
Contest Date: 11/14/2023
Final Order: 05/30/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 05/30/2024 | $6,562.80 | Serious | ||
| Penalty | C: Contested | 12/18/2023 | $10,938.00 | Serious | ||
| Penalty | Z: Issued | 10/20/2023 | $10,938.00 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.305(j)(2)(v):A receptacle installed outdoors in a location protected from the weather or in other damp locations did not have an enclosure for the receptacle that was weatherproof when the receptacle was covered: On or about April 26, 2023, and times prior thereto, in the fabrication shop, there were three outdoor electric receptacles that did not have a weatherproof enclosure.