Violation Detail
Standard Cited: 19100269 O02 I Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1659028.015
Citation: 01004
Citation Type: Serious
Abatement Date: 10/02/2023 2
Initial Penalty: $15,625.00
Current Penalty: $0.00
Issuance Date: 09/13/2023
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 10
Report ID: 0627700
Contest Date:
Final Order: 10/10/2023
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/10/2023 | $0.00 | 10/02/2023 | Serious | |
Penalty | Z: Issued | 09/13/2023 | $15,625.00 | 10/02/2023 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.269(o)(2)(i): Work practices for the protection of each worker was not established from the hazards of high-voltage or high-power testing at all test areas, temporary and permanent: On or about March 22, 2023, at a remote location, employees opened and began to work on the internal parts of a transformers without testing the wiring to ensure the system was de-energized, exposing employees to the hazard of coming in contact with energized parts.