Violation Detail
Standard Cited: 19100147 D04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1655473.015
Citation: 01004
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,938.00
Current Penalty: $0.00
Issuance Date: 07/10/2023
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 09/01/2023
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order: 08/03/2023
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/03/2023 | $0.00 | 09/01/2023 | Serious | |
Penalty | Z: Issued | 07/10/2023 | $10,938.00 | 07/24/2023 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.147(d)(4)(i):Lockout or tagout devices were not affixed to each energy isolating device by authorized employees: On or about March 3, 2023, the employer did not ensure that lockout or tagout devices were affixed to each energy isolating device by authorized employees prior to changing clean-in-place connections on the CIP Flow Plate on the Cheesemaker Catwalk.