Violation Detail
Standard Cited: 19100269 M02 I Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1539931.015
Citation: 01004
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,288.00
Current Penalty: $7,372.80
Issuance Date: 10/26/2021
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 11/22/2021
Gravity: 10
Report ID: 0626300
Contest Date:
Final Order: 12/15/2021
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/15/2021 | $7,372.80 | 11/22/2021 | Serious | |
Penalty | Z: Issued | 10/26/2021 | $12,288.00 | 11/22/2021 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.269(m)(2)(i):The employee that the employer designates pursuant to paragraph (m)(2) of this section as being in charge of the clearance did not make a request of the system operator to deenergize the particular section of line or equipment. The designated employee becomes the employee in charge (as this term is used in paragraph (m)(3) of this section) and is responsible for the clearance. (a) On or about June 29, 2021, two employees installing electrical equipment were exposed to an electrical hazard when the requirements of paragraph (m)(3) of this section were not met.