Violation Detail
Standard Cited: 19100269 M03 VII Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1484786.015
Citation: 01004
Citation Type: Serious
Abatement Date: 04/01/2021 2
Initial Penalty: $9,446.00
Current Penalty: $6,612.20
Issuance Date: 01/15/2021
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0626600
Contest Date:
Final Order: 01/29/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/29/2021 | $6,612.20 | 04/01/2021 | Serious | |
Penalty | Z: Issued | 01/15/2021 | $9,446.00 | 02/04/2021 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.269(m)(3)(vii):The employer did not ensure the installation of protective grounds as required by paragraph (n) of this section: On or about July 19, 2020, employees were exposed to electrical hazards while working on a downed power line without installing grounds.