Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1371237.015
Citation: 01004
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $11,366.00
Current Penalty: $9,000.00
Issuance Date: 05/17/2019
Nr Instances: 1
Nr Exposed: 25
Abatement Date: 07/05/2019
Gravity:
Report ID: 0418100
Contest Date:
Final Order: 06/07/2019
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/07/2019 | $9,000.00 | 07/05/2019 | Other | |
| Penalty | Z: Issued | 05/17/2019 | $11,366.00 | 07/05/2019 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed. On 1/14/19, at the Bethlehem facility, the employer did not ensure a periodic inspection was performed in accordance with the standard. Deficiencies included: a - Missing energies and magnitudes of those energies on procedures b - For the procedures reviewed during the periodic inspection, it did not include a review between at least 2 authorized employees