Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1291715.015
Citation: 01004
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,934.00
Current Penalty: $7,760.40
Issuance Date: 02/23/2018
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 04/11/2018
Gravity: 10
Report ID: 0729700
Contest Date:
Final Order: 03/15/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/15/2018 | $7,760.40 | 04/11/2018 | Serious | |
Penalty | Z: Issued | 02/23/2018 | $12,934.00 | 04/11/2018 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: Employees engaged in repair and maintenance activities at the following pieces of equipment in all 3 buildings of the facility were exposed to electrical, struck-by and caught-between hazards in that machine specific energy control procedures had not been developed and implemented. a) FA 1050S CNC Mill b) Cincinnati FTV840 CNC Mill c) Okuma Genos M560-V CNC machines d) Mag Fadal VMC 3016 FX e) VMC 4020 f) VMC 6030 machines g) Mori Seiki CNC machine h) Bertsche Xi Mill CNC machines i) Makino Mag 3 EX CNC Mill machines 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.