Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 1209779.015
Citation: 01004
Citation Type: Serious
Abatement Date: 07/07/2017 2
Initial Penalty: $8,149.00
Current Penalty: $6,111.75
Issuance Date: 06/09/2017
Nr Instances: 1
Nr Exposed: 12
Related Event Code (REC): C
Gravity: 5
Report ID: 0524530
Contest Date: 07/03/2017
Final Order: 09/24/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/24/2018 | $6,111.75 | 07/07/2017 | Serious | |
Penalty | C: Contested | 07/03/2017 | $8,149.00 | 07/07/2017 | Serious | |
Penalty | Z: Issued | 06/09/2017 | $8,149.00 | 07/07/2017 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: In the old section of the warehouse, by paint sorting operation, employees were exposed to electrical shock hazards when the employer failed to ensure that each circuit breaker was labeled to indicate its purpose.