Violation Detail
Standard Cited: 19100147 D The control of hazardous energy (lockout/tagout).
Inspection Nr: 1177905.015
Citation: 01004
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,471.00
Current Penalty: $12,471.00
Issuance Date: 12/22/2016
Nr Instances: 1
Nr Exposed: 11
Abatement Date: 02/15/2017
Gravity: 10
Report ID: 0521400
Contest Date:
Final Order: 01/25/2017
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/25/2017 | $12,471.00 | 02/15/2017 | Serious | |
Penalty | Z: Issued | 12/22/2016 | $12,471.00 | 01/30/2017 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.147(d): The established procedure for the application of energy control (the lockout or tagout procedures) did not cover the actions listed in and was not done in sequence as required by 29 CFR 1910.147(d)(1)-(6): The worker assigned to clean Blender No. 10 in the northwest, isolated blending room on September 13, 2016 did not verify that isolation and deenergization of the blenders three 480-volt disconnects had been accomplished prior to cleaning the blender. Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).