Violation Detail
Standard Cited: 19100269 D02 V Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1112592.015
Citation: 01004
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,000.00
Current Penalty: $5,000.00
Issuance Date: 06/07/2016
Nr Instances: 1
Nr Exposed: 24
Abatement Date: 05/25/2017
Gravity: 5
Report ID: 0524530
Contest Date: 06/30/2016
Final Order: 05/25/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/25/2017 | $5,000.00 | 05/25/2017 | Serious | |
Penalty | C: Contested | 07/01/2016 | $5,000.00 | 07/25/2016 | Serious | |
Penalty | Z: Issued | 06/07/2016 | $5,000.00 | 07/25/2016 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.269(d)(2)(v): The employer did not conduct periodic inspection of the energy control procedure at least annually to ensure that the procedure and the provisions of paragraph (d) of this section are being followed. The employer did not ensure that periodic inspections of the energy control procedures were conducted at least annually such as but not limited to the SDA clean out process.