Violation Detail
Standard Cited: 19100217 C03 IV D Mechanical power presses.
Inspection Nr: 1647325.015
Citation: 01003D
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,938.00
Current Penalty: $0.00
Issuance Date: 05/12/2023
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 06/08/2023
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 05/31/2023
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/31/2023 | $0.00 | 06/08/2023 | Serious | |
Penalty | Z: Issued | 05/12/2023 | $10,938.00 | 06/08/2023 | Serious |
Text For Citation: 01 Item/Group: 003D Hazard:
29 CFR 1910.217(c)(3)(iv)(d): Point of operation devices. Each pull-out device in use shall be visually inspected and checked for proper adjustment at the start of each operator shift, following a new die set-up, and when operators are changed. Necessary maintenance or repair or both shall be performed and completed before the press is operated. Records of inspections and maintenance shall be kept in accordance with paragraph (e) of this section. a) On or about January 20, 2023, the employer did not ensure the pull-out device in use on the Punch 21 Walsh Press & Die Co full revolution press was visually inspected and checked for proper adjustment at the start of each operator shift. The pullbacks were last set up on January 19, 2023.