Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1165746.015
Citation: 01003D
Citation Type: Serious
Abatement Date: 02/15/2017 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/20/2017
Nr Instances: 1
Nr Exposed: 60
Related Event Code (REC):
Gravity: 10
Report ID: 0418100
Contest Date:
Final Order: 02/17/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/17/2017 | $0.00 | 02/15/2017 | Serious | |
Penalty | Z: Issued | 01/20/2017 | $0.00 | 02/15/2017 | Serious |
Text For Citation: 01 Item/Group: 003D Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: On or about 7/26/2016 throughout the facility, employees performed tasks such as but not limited to cleaning, maintenance, and troubleshooting of a variety of machines and equipment such as but not limited to Pre Expanders 1-8 and machinery along the HK Cup Lines. Written HECP (Hazardous Energy Control Program) procedures developed by the company had not been inspected within the last year. Procedures that were not inspected include, but are not limited to the following: a. Lockout/Tagout Procedure for the HK Cup Machines b. Lockout/Tagout Procedure for the Hydraulic Pump c. Lockout/Tagout Procedure for the Printer OFF Line d. Lockout/Tagout Procedure for the HK Printer e. Lockout/Tagout Procedure for the Pre Expander 1 thru 8