Standard Cited: 19100147 D The control of hazardous energy (lockout/tagout).
Inspection Nr: 1661120.015
Citation: 01003C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/26/2023
Nr Instances: 3
Nr Exposed: 3
Abatement Date: 09/15/2023
Gravity: 10
Report ID: 0524500
Contest Date:
Final Order: 08/18/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/18/2023 | $0.00 | 09/15/2023 | Serious | |
Penalty | Z: Issued | 07/26/2023 | $0.00 | 09/15/2023 | Serious |
Text For Citation: 01 Item/Group: 003C Hazard:
29 CFR 1910.147(d): The established procedure for the application of energy control (the lockout or tagout procedures) did not cover the actions listed in and was not done in sequence as required by 29 CFR 1910.147(d)(1)-(6): a. On or about April 21, 2023, employees were exposed to amputation hazards while cleaning cardboard out of and performing maintenance on the shredder and the employer failed to implement energy control application steps as the machine was not shut down or turned off to perform the servicing work [per the 1910.147(d)(2) requirements]. As a result, the remaining applicable energy control elements, involving machine isolation [(d)(3)], LOTO device application [(d)(4)], dissipation of residual energy [(d)(5)(i)], and verification of isolation [(d)(6)], were not implemented to protect employees from machine servicing hazards. b. On or about April 21, 2023, employees were exposed to amputation hazards while adjusting the rails of and performing maintenance on the Flexo Folder (new) and the employer failed to implement energy control application steps as the machine was not shut down or turned off to perform the servicing work [per the 1910.147(d)(2) requirements]. As a result, the remaining applicable energy control elements, involving machine isolation [(d)(3)], LOTO device application [(d)(4)], dissipation of residual energy [(d)(5)(i)], and verification of isolation [(d)(6)], were not implemented to protect employees from machine servicing hazards. c. On or about April 21, 2023, employees were exposed to amputation hazards while adjusting the rails of and performing maintenance on the Flexo Folder (old) and the employer failed to implement energy control application steps as the machine was not shut down or turned off to perform the servicing work [per the 1910.147(d)(2) requirements]. As a result, the remaining applicable energy control elements, involving machine isolation [(d)(3)], LOTO device application [(d)(4)], dissipation of residual energy [(d)(5)(i)], and verification of isolation [(d)(6)], were not implemented to protect employees from machine servicing hazards.