Standard Cited: 19100169 B03 I Air receivers.
Inspection Nr: 1571874.015
Citation: 01003C
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/18/2022
Nr Instances: 2
Nr Exposed: 8
Abatement Date:
Gravity: 1
Report ID: 0112000
Contest Date:
Final Order: 03/25/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/25/2022 | $0.00 | Serious | ||
Penalty | Z: Issued | 02/18/2022 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 003C Hazard:
29 CFR 1910.169(b)(3)(i): Compressed air receiver(s) were not equipped with one or more spring-loaded safety valves: A. Kummer Cell: On, or about, January 10, 2022, two shop fabricated air receiver tanks were used to supply compressed air to bench mounted pneumatic presses. The tanks were not provided with pressure relief valves. B. Production Floor: On, or about, January 21, 2022, a pressure relief valve was not provided on the air receiver tank for Machine #2502, a Technica Multi-station drilling and edging machine.