Standard Cited: 19100107 D11 Spray finishing using flammable and combustible materials.
This violation item has been deleted.
Inspection Nr: 1308345.015
Citation: 01003C
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/21/2018
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/25/2019
Gravity: 5
Report ID: 0316700
Contest Date: 10/12/2018
Final Order: 01/09/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/09/2019 | $0.00 | 03/25/2019 | Serious | |
Penalty | C: Contested | 10/15/2018 | $0.00 | 03/25/2019 | Serious | |
Penalty | Z: Issued | 09/21/2018 | $0.00 | 03/25/2019 | Serious |
Text For Citation: 01 Item/Group: 003C Hazard:
29 CFR 1910.107(d)(11): Air intake openings to rooms containing spray finishing operations were not adequate for the efficient operation of exhaust fans and were not located as to minimize the creation of dead air pockets: (a) Powder Coating Operation - The two spray rooms used for the powder coating operation were not provided with adequate air intakes to minimize dead pockets in the rooms, on or about April 11, 2018. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.