Standard Cited: 19100333 B02 II D Selection and use of work practices
Inspection Nr: 1806333.015
Citation: 01003B
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/21/2025
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 10/09/2025
Gravity: 10
Report ID: 0214200
Contest Date: 09/17/2025
Final Order:
Related Event Code (REC): A;R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | C: Contested | 09/18/2025 | $0.00 | 10/09/2025 | Serious | |
| Penalty | Z: Issued | 08/21/2025 | $0.00 | 10/09/2025 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1910.333(b)(2)(ii)(D): Stored non-electrical energy in devices that could reenergize electric circuit parts shall be blocked or relieved to the extent that the circuit parts could not be accidentally energized by the device: Location: 60 Earhart Drive. Newark, NJ 07114 - Rail Link SOP 11-12 a: The employer did not develop and implement procedures to ensure electrical circuit parts did not become energized by non-electrical energy caused by rail cars moving through the rail crossover devices. Employees were exposed to electrocution hazards while replacing fuses in an electrical panel as a train was towed through the crossover, which created an electrical backfeed into the panel. Violation occurred on or about February 25, 2025.