Violation Detail
Standard Cited: 19100303 B07 IV General.
Inspection Nr: 1791333.015
Citation: 01003B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/22/2025
Nr Instances: 2
Nr Exposed: 5
Abatement Date: 05/16/2025
Gravity: 10
Report ID: 1032500
Contest Date:
Final Order: 05/15/2025
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/15/2025 | $0.00 | 05/16/2025 | Other | |
Penalty | Z: Issued | 04/22/2025 | $0.00 | 05/16/2025 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1910.303(b)(7)(iv): There were damaged parts that may adversely affect safe operation or mechanical strength of the equipment, such as parts that are broken, bent, cut, or deteriorated by corrosion, chemical action or overheating. a) Building 3, Speed Cut, Timber Mill, MH6G - 20, S/N Y0559: On and prior to December 4, 2024, employees worked within three feet of the main power cable which had been spliced with wire nuts and tape. Conductors were visible between the tape and cable jacket. The power cable is a SEOW-A, 4,4, which is rated for a maximum of 600 volts. b) Building 3, Speed Cut, Timber Mill, MH6G - 20, S/N Y0559: On and prior to December 4, 2024, employees worked within three feet of a cable which had a damaged jacket and exposed internal conductors.