Violation Detail
Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 1628330.015
Citation: 01003B
Citation Type: Serious
Abatement Status: Not Completed - AD Discretion
Initial Penalty: $15,625.00
Current Penalty: $0.00
Issuance Date: 04/13/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 04/19/2023
Gravity: 10
Report ID: 0213900
Contest Date: 05/08/2023
Final Order: 05/02/2024
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 05/02/2024 | $0.00 | 04/19/2023 | Serious | |
Penalty | C: Contested | 08/08/2023 | $15,625.00 | 04/19/2023 | Serious | |
Penalty | Z: Issued | 04/13/2023 | $15,625.00 | 04/19/2023 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1926.416(a)(3): Before work began, the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring any person, tool, or machine into physical or electrical contact with the electric power circuit. (a) Camden anchor on the Franklin Bridge track 2, Camden, NJ: Workers were exposed to electrical hazards when they entered on to the PATCO tracks without confirming that the 700 VDC third rail was de-energized on or about 10/14/2022. NOTE: IN ADDITION TO ABATEMENT CERTIFICATION, THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT DOCUMENTATION FOR THIS ITEM, FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.