Standard Cited: 19100333 B02 II A Selection and use of work practices
Inspection Nr: 1483135.015
Citation: 01003B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/18/2020
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 01/25/2021
Gravity: 10
Report ID: 0523400
Contest Date:
Final Order: 01/20/2021
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/20/2021 | $0.00 | 01/25/2021 | Serious | |
| Penalty | Z: Issued | 12/18/2020 | $0.00 | 01/25/2021 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1910.333(b)(2)(ii)(A): Safe procedures for deenergizing circuits and equipment were not determined before circuits and equipment were deenergized. (a) On or about July 13, 2020, safe deenergization procedures were not developed and provided to maintenance employee(s) trouble shooting and repairing a Ducane Air Conditioning Unit (Model No. AC10B24 & Serial No. 6513090551), exposing the employee to an electrical shock hazard.
Translate