Violation Detail
Standard Cited: 19100147 C04 II C The control of hazardous energy (lockout/tagout).
Inspection Nr: 1385578.015
Citation: 01003B
Citation Type: Serious
Abatement Date: 09/30/2019
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/13/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0419400
Contest Date: 10/07/2019
Final Order:
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 11/25/2019 | $0.00 | 09/30/2019 | Serious | |
Penalty | Z: Issued | 09/13/2019 | $0.00 | 09/30/2019 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1910.147(c)(4)(ii)(C): The energy control procedure did not clearly and specifically outline the steps for placement, removal and transfer of lockout devices or tagout devices and the responsibility for them: (a) Department 126, Poletype Division, Regulator Tank Shop, Leak Test and Repair - On or about March 15, 2019, the employer did not ensure that the lockout procedures clearly and specifically explain the placement of the safety chains for the leak test device to isolate the gravitational energy source, exposing employees to struck by hazards.