Standard Cited: 19100147 C06 I C The control of hazardous energy (lockout/tagout).
Inspection Nr: 1253142.015
Citation: 01003B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,934.00
Current Penalty: $0.00
Issuance Date: 01/19/2018
Nr Instances: 4
Nr Exposed: 14
Abatement Date: 10/01/2018
Gravity: 10
Report ID: 0418100
Contest Date: 02/14/2018
Final Order: 09/05/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/05/2018 | $0.00 | 10/01/2018 | Serious | |
Penalty | C: Contested | 02/16/2018 | $12,934.00 | 02/14/2018 | Serious | |
Penalty | Z: Issued | 01/19/2018 | $12,934.00 | 02/14/2018 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1910.147(c)(6)(i)(C): Where lockout was used for energy control, the periodic inspection did not include a review, between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure being inspected: On or about 8/8/2017 in the production areas at 1 Wingfoot Way NE, Social Circle, GA: Where employees performed maintenance and or service on equipment such as the four (4) flat press and mill equipment. The employer failed to ensure that all authorized employees were included in the review of the periodic procedure.