Violation Detail
Standard Cited: 19260651 J02 Specific Excavation Requirements.
Inspection Nr: 1238180.015
Citation: 01003B
Citation Type: Serious
Abatement Status: Not Completed - AD Discretion
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/28/2017
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 08/03/2017
Gravity: 1
Report ID: 0523400
Contest Date: 10/19/2017
Final Order: 03/23/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 03/23/2018 | $0.00 | 08/03/2017 | Serious | |
| Penalty | C: Contested | 11/17/2017 | $0.00 | 08/03/2017 | Serious | |
| Penalty | Z: Issued | 07/28/2017 | $0.00 | 08/03/2017 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1926.651(j)(2): Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary. (a) The employer did not ensure that all portions of the spoil pile was at least 2 feet away from the edge of the excavation.