Violation Detail
Standard Cited: 19260854 D Removal of walls, masonry sections, and chimneys.
Inspection Nr: 1211686.015
Citation: 01003B
Citation Type: Serious
Abatement Date: 08/07/2017 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/19/2017
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0418600
Contest Date:
Final Order: 08/18/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/18/2017 | $0.00 | 08/07/2017 | Serious | |
Penalty | Z: Issued | 07/19/2017 | $0.00 | 08/07/2017 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1926.854(d): The structural or load-supporting members were cut or removed before all stories above such a floor were demolished and removed: a) Five Story Building: On or about February 14, 2017 and at times prior thereto, the employer did not ensure all stories above were demolished and removed prior to demolishing portions of the steel framing, wooden floors, and brick walls on each respective lower level of the building which exposed employees to death and other injuries associated with falls or being struck-by and crushed-by collapsing and falling portions of the structure.