Violation Detail
Standard Cited: 19100219 H01 Mechanical power-transmission apparatus.
Inspection Nr: 1107788.015
Citation: 01003B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/21/2016
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 08/16/2016
Gravity: 1
Report ID: 0418400
Contest Date: 08/15/2016
Final Order: 07/20/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/20/2017 | $0.00 | 08/16/2016 | Serious | |
Penalty | C: Contested | 08/24/2016 | $0.00 | 08/16/2016 | Serious | |
Penalty | Z: Issued | 07/21/2016 | $0.00 | 08/16/2016 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1910.219(h)(1): Projecting key(s), setscrew(s), or other projections in revolving part(s) were not removed, made flush, or guarded by metal cover(s). a). Shelling Plant - On or about and times prior to February 9, 2016, there were projecting square head setscrews located on the rear horizontal shaft of the Whole Shaker (secondary sheller) that were not guarded, thus exposing employees to a caught-in hazard.