Violation Detail
Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
Inspection Nr: 974837.015
Citation: 01003A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 09/22/2014
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 12/30/2014
Gravity: 10
Report ID: 0522000
Contest Date: 10/15/2014
Final Order: 01/20/2015
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/20/2015 | $7,000.00 | 12/30/2014 | Serious | |
Penalty | C: Contested | 10/17/2014 | $7,000.00 | 10/17/2014 | Serious | |
Penalty | Z: Issued | 09/22/2014 | $7,000.00 | 10/17/2014 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1910.147(d)(3): Machine or equipment isolation. All energy isolating devices that are needed to control the energy to the machine or equipment shall be physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s). (a) During a product line change of the 72 inch Braner Slitting Line, affected employees removed scrap from the back of the little shear on the 72 inch Braner Slitting Line without first isolating the energy sources, thereby exposing them to the unexpected start up of the shear.