Violation Detail
Standard Cited: 19100036 D01 Design and construction requirements for exit routes.
Inspection Nr: 313815896
Citation: 01003A
Citation Type: Serious
Abatement Status: X
Initial Penalty: $7,000.00
Current Penalty: $2,620.00
Issuance Date: 04/27/2012
Nr Instances: 2
Nr Exposed: 14
Abatement Date: 05/23/2012
Gravity:
Report ID: 0452110
Contest Date:
Final Order:
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/22/2012 | $2,620.00 | 05/23/2012 | Serious | |
| Penalty | Z: Issued | 04/27/2012 | $7,000.00 | 05/23/2012 | Serious |