Violation Detail
Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
Inspection Nr: 1800723.015
Citation: 01003A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,093.00
Current Penalty: $0.00
Issuance Date: 07/18/2025
Nr Instances: 6
Nr Exposed: 12
Abatement Date: 09/04/2025
Gravity: 1
Report ID: 0625500
Contest Date:
Final Order: 08/12/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/12/2025 | $0.00 | 09/04/2025 | Serious | |
Penalty | Z: Issued | 07/18/2025 | $7,093.00 | 09/04/2025 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going integrity of process equipment. On or about 1/29/2025, for the PSM-covered process at the Lubrizol facility, written procedures were not established for : a) Testing the Pressure Transmitter PT-300 on reactor R3 (200-PID-0005 Rev. B). b) Testing the Pressure Transmitter PT-300 on reactor R6 (200-PID-0006 Rev. G). c) Testing the Pressure Transmitter PT-200 on reactor R5 (200-PID-0012 Rev. D). d) Testing the Temperature Indicator Controller TIC-100 on reactor R5 (200-PID-0012 Rev. D). e) Testing the Temperature Control Valves TCV-300 and TCV-400 on reactor R5 (200-PID-0012 Rev. D). f) Testing and inspecting piping.