Violation Detail
Standard Cited: 19100269 D02 V D Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1425017.015
Citation: 01003A
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $5,304.00
Current Penalty: $0.00
Issuance Date: 09/03/2019
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 10/01/2019
Gravity: 5
Report ID: 0636900
Contest Date: 09/26/2019
Final Order: 03/13/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | R: Review Commission | 03/13/2020 | $0.00 | 10/01/2019 | Serious | |
| Penalty | C: Contested | 03/03/2020 | $5,304.00 | 10/01/2019 | Serious | |
| Penalty | Z: Issued | 09/03/2019 | $5,304.00 | 10/01/2019 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1910.269(d)(2)(v)(D): Where tagout is used for energy control, the periodic inspection shall include a review, between the inspector and each authorized and affected employee, of that employee's responsibilities under the energy control procedure being inspected, and the elements set forth in paragraph (d)(2)(vii) of this section. At the facility located at 12567 FM 3430 Vernon, Texas: the employer did not perform periodic inspections with the employee assigned to trouble shoot the transformer Rectifier equipment in the Precipitator Control room. The tag-out procedure was not used and the employee was exposed to electric shock and arc flash hazards.
Translate