Violation Detail
Standard Cited: 19260754 A Structural steel assembly.
Inspection Nr: 1330086.015
Citation: 01003A
Citation Type: Serious
Abatement Date: 01/15/2019 5
Initial Penalty: $12,934.00
Current Penalty: $12,934.00
Issuance Date: 01/03/2019
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0317900
Contest Date:
Final Order: 03/18/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 01/03/2019 | $12,934.00 | 01/15/2019 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1926.754(a): Structual stability was not maintained at all times during the erection process. a) 309 Upper Stump Rd. Chalfont, PA - on or about July 13, 2018, employees were performing steel erection activities erecting structural steel for a mezzanine, but the structural stability was not maintained at all times during the erection process.