Violation Detail
Standard Cited: 19260454 B02 Training requirements.
Inspection Nr: 1301606.015
Citation: 01003A
Citation Type: Serious
Abatement Date: 07/09/2018 2
Initial Penalty: $3,880.00
Current Penalty: $2,328.00
Issuance Date: 06/19/2018
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 08/06/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/06/2018 | $2,328.00 | 07/09/2018 | Serious | |
Penalty | Z: Issued | 06/19/2018 | $3,880.00 | 07/09/2018 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1926.454(b)(2): The employer did not have each employee who was involved in erecting, disassembling, moving, operating, repairing, maintaining, or inspecting a scaffold trained by a competent person to recognize any hazards associated with the correct procedures for erecting, disassembling, moving, operating, repairing, inspecting, and maintaining the supported fabricated scaffold: a) At the job site, on or about March 8, 2018, the employees erecting and operating tubular welded frame scaffolding had not been trained on the correct procedures for erecting, moving, operating, inspecting and maintaining the scaffold.