Violation Detail
Standard Cited: 19100147 C04 II C The control of hazardous energy (lockout/tagout).
Inspection Nr: 1252686.015
Citation: 01003A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,097.00
Current Penalty: $3,300.00
Issuance Date: 01/22/2018
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 02/15/2018
Gravity: 1
Report ID: 0418100
Contest Date:
Final Order: 02/13/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/13/2018 | $3,300.00 | 02/15/2018 | Serious | |
| Penalty | Z: Issued | 01/22/2018 | $6,097.00 | 02/15/2018 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1910.147(c)(4)(ii)(C): The energy control procedure did not clearly and specifically outline the steps for placement, removal and transfer of lockout devices or tagout devices and the responsibility for them: On or about August 3, 2017, the lockout/tagout procedures did not specifically outline the order that locks should be removed from electrical and air energy sources for equipment such as, but not limited to, Norfield magnum, Kval 950 hinge prep machine, Kval 920 strike prep machine, Norfield 5000, Norfield 4000, Norfield Eagle, and Norfield 1020. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).