Violation Detail
Standard Cited: 19260502 D06 III Fall protection systems criteria and practices.
Inspection Nr: 1249360.015
Citation: 01003A
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $7,985.00
Current Penalty: $7,985.00
Issuance Date: 08/25/2017
Nr Instances: 1
Nr Exposed: 4
Abatement Date:
Gravity: 10
Report ID: 0215800
Contest Date:
Final Order: 10/02/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 08/25/2017 | $7,985.00 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1926.502(d)(6)(iii): A snap hook not of the locking type was engaged (i) directly to webbing, rope or wire rope; (ii) to each other (iii) to a Dee-ring to which another snap hook or other connector is attached;(iv) to a horizontal lifeline; or (v) to any object which is incompatibly shaped or dimensioned in relation to the snap hook such that unintentional disengagement could occur by the connected object being able to depress the snap hook keeper and release itself: a) South side of roof, east end, on or about 7-20-17: Four employees were working at the edge of a barrel roof with multiple snap hooks engaged to a single D-ring anchor, exposing the employees to a fall hazard of 26 feet 3 inches to the ground below. b) South side of roof, west end, on or about 7-20-17: Four employees were working at the edge of a barrel roof with multiple snap hooks engaged to a single D-ring anchor, exposing the employees to a fall hazard of 10 feet 8 inches to a lower roof.