Standard Cited: 19100179 J02 Overhead and gantry cranes.
Inspection Nr: 1188860.015
Citation: 01003A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $11,408.00
Current Penalty: $8,149.00
Issuance Date: 03/06/2017
Nr Instances: 2
Nr Exposed: 2
Abatement Date: 08/30/2017
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order: 04/04/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | $8,149.00 | 08/30/2017 | Serious | ||
Penalty | I: Informal Settlement | 04/04/2017 | $8,149.00 | 04/28/2017 | Serious | |
Penalty | Z: Issued | 03/06/2017 | $11,408.00 | 04/03/2017 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1910.179(j)(2): The following items were not being inspected for defects at intervals as defined in paragraph (j)(1)(ii) of this section or as specifically indicated, including observation during operation for any defects which might appear between regular inspections: On or about November 03, 2016 employees were using a gantry crane in the acid wash area to lift and support the boat when manually acid washing a boat hull after it failed inspection on August 27, 2015. The gantry crane was not re-inspected before being used in 2016.