Violation Detail
Standard Cited: 19260416 A01 General requirements.
Inspection Nr: 1006396.015
Citation: 01003A
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $5,390.00
Current Penalty: $3,500.00
Issuance Date: 04/29/2015
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 05/11/2015
Gravity: 10
Report ID: 0521400
Contest Date: 05/06/2015
Final Order: 12/30/2015
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 12/30/2015 | $3,500.00 | 05/11/2015 | Serious | |
Penalty | C: Contested | 05/06/2015 | $5,390.00 | 05/11/2015 | Serious | |
Penalty | Z: Issued | 04/29/2015 | $5,390.00 | 05/11/2015 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1926.416(a)(1): Employees were permitted to work in such proximity to electric power circuits that employees could contact the electric power circuit in the course of work and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: On or about November 4, 2014, at the above addressed jobsite, employees engaged in residential roofing operations were working two (2) feet three (3) inches away from an energized aerial electric service drop, exposing employees to electric shock and falls of twenty-two (22) feet four (4) inches. Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).