Violation Detail
Standard Cited: 19260451 F07 General requirements.
Inspection Nr: 1003442.015
Citation: 01003A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,300.00
Current Penalty: $6,300.00
Issuance Date: 04/14/2015
Nr Instances: 1
Nr Exposed: 17
Abatement Date: 05/01/2015
Gravity: 10
Report ID: 0936300
Contest Date:
Final Order: 05/07/2015
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/07/2015 | $6,300.00 | 05/01/2015 | Serious | |
| Penalty | Z: Issued | 04/14/2015 | $6,300.00 | 05/01/2015 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1926.451(f)(7): Scaffolds shall be erected, moved, dismantled, or altered only under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration. Such activities shall be performed only by experienced and trained employees selected for such work by the competent person. Dusit Thani Hotel Jobsite, Sixth Floor, Banquet Room 1 and 2: Pacific Rim Land Development permitted a four tier fabricated frame orange mobile scaffold to be moved by employees not under the supervision and direction of a competent person qualified in moving mobile scaffolds. On October 18, 2014, the mobile scaffold toppled over fatally injuring a plumber. The scaffold was hazardous in that the scaffold frame legs were not designed with holes to accept mobile scaffold wheel stem pins to prevent the wheels from coming out of the frame legs; and the height to base ratio of the mobile scaffold was greater than 4 to 1. When the orange scaffold toppled it was measured to be 16 feet, 7.5 inches tall and 4 feet wide.