Powered by GoogleTranslate

Violation Detail

Standard Cited: 19100024 F Step bolts and manhole steps.

Inspection Nr: 986883.015

Citation: 01003

Citation Type: Serious

Abatement Status: Abatement Completed

Initial Penalty: $3,740.00

Current Penalty: $3,740.00

Issuance Date: 01/15/2015

Nr Instances: 1

Nr Exposed: 3

Abatement Date: 03/05/2015

Gravity: 5

Report ID: 0418400

Contest Date:

Final Order: 02/09/2015

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 02/09/2015 $3,740.00 03/05/2015 Serious  
Penalty Z: Issued 01/15/2015 $3,740.00 03/05/2015 Serious  

Text For Citation: 01 Item/Group: 003 Hazard:

29 CFR 1910.24(f): Rise height and tread width were not uniform throughout any flight of stairs including any foundation structure used as one or more treads of the stairs: A) Power House Stairs to 8th floor coal bunker, on or about September 23, 2014, the distance between the top step and the floor was not uniform in that the top riser was measured at approximately 15 inches high and the other step risers were approximately 8 inches high, exposing employees to a fall hazard.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.