Violation Detail
Standard Cited: 19260451 C01 II General requirements.
Inspection Nr: 918413.015
Citation: 01003
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $2,000.00
Current Penalty: $2,000.00
Issuance Date: 09/24/2013
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 10/02/2013
Gravity: 5
Report ID: 0111400
Contest Date:
Final Order: 10/18/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 09/24/2013 | $2,000.00 | 10/02/2013 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.451(c)(1)(ii): Guys, ties, and/or braces were not installed according to the scaffold manufacturer's recommendations or at the closest horizontal member to the 4:1 height and repeated vertically at locations of horizontal members every 20 feet (56.1 m) or less thereafter for scaffolds 3 feet ((0.91 m) wide or less, and every 26 feet (7.9 m) or less therafter for scaffolds greater than 3 feet (0.91m) wide. Jobsite: pump jack scaffold at south side of building The pump jack scaffold was only braced near its top: the braces were located at a height of more than 36 feet.