Violation Detail
Standard Cited: 19100119 L01 Process safety management of highly hazardous chemicals.
Inspection Nr: 901522.015
Citation: 01003
Citation Type: Serious
Abatement Date: 04/15/2014 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 10/11/2013
Nr Instances: 1
Nr Exposed: 20
Related Event Code (REC):
Gravity: 10
Report ID: 0626700
Contest Date: 11/01/2013
Final Order: 02/25/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 04/16/2014 | $7,000.00 | 11/14/2013 | Serious | |
Penalty | C: Contested | 04/16/2014 | $7,000.00 | 11/14/2013 | Serious | |
Penalty | F: Formal Settlement | 02/25/2014 | $0.00 | 11/14/2013 | Serious | |
Penalty | F: Formal Settlement | 02/25/2014 | $7,000.00 | 04/15/2014 | Serious | |
Penalty | Z: Issued | 10/11/2013 | $7,000.00 | 11/14/2013 | Serious | |
Penalty | Z: Issued | 10/11/2013 | $7,000.00 | 11/14/2013 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.119(j)(2): The employer did not implement written procedures to maintain the on-going integrity of process equipment a) On April 17, 2013 or at times prior thereto in the Catalytic Hydrodesulfurization Unit #2 (CHD-2) of the ExxonMobil Refinery in Beaumont, Texas, the employer failed to implement maintenance procedures to safely open process equipment. b) On April 17, 2013 or at times prior thereto in the Catalytic Hydrodesulfurization Unit #2 (CHD-2) of the ExxonMobil Refinery in Beaumont, Texas, the employer failed to develop procedures that would adequately ensure integrity of equipment when chemical washing the E-1 exchangers to clear the exchangers of petroleum hydrocarbons. 29 CFR 1910.119(l)(1): The employer did not implement procedures to manage changes to process chemicals, technology, equipment, and procedures, and changes to facilities that affect a covered process. On April 17, 2013 ExxonMobil did not follow its management of change process when it deviated from Maintenance Procedure 203-Procedure for Line Equipment Opening and Safe Blinding during the performance of maintenance on the E-1 heat exchangers in the Catalytic Hydrodesulphurization Unit #2 (CHD-2) of the ExxonMobil Refinery in Beaumont, Texas.